In the charter: Issuance of Certificate of Occupancy
Under PD 1096 (the National Building Code), Section 309, the Office of the Municipal Engineer & Building Official (MEBO) issues a Certificate of Occupancy once construction is complete and before the building is occupied. MEBO checks that the completed building follows the standards and the plans attached to the approved Building Permit; any revisions made during construction must be reflected in the as-built plans.
- Processing time
- Not stated in the charter
- Fees
- Fees apply. See the steps below.
- Who can apply
- Anyone
- Type of transaction
- Simple, complex or highly technical · government to citizen · government to business · government to government
Simple, complex and highly technical applications follow the same steps with different review times (pages 94–105). The charter does not print a total processing time for these applications.
Fees are computed from the National Building Code schedule of fees and other charges on pages 108–125 of the charter.
What to bring
Tick items off as you gather them. Nothing is saved or sent anywhere.
Conditional requirements
Step by step
Apply
Step 1: Submit the application forms and documentary requirements
The office will
- Receive and assess the submitted documents
- Conduct site inspection and verification
- Evaluate the documents
- Fee
- Free
- Handled by
- Engineer I, Engineer II MEBO
Pay
Step 2: Receive the order of payment and pay the corresponding fees
The office will
- Calculate and prepare fees based on the NBCDO schedule of fees and other charges
- Issue the payment slip
- Endorse the documents to the Bureau of Fire Protection
- Fee
- Based on the NBCDO schedule of fees and other charges
- Handled by
- Engineer I MEBO, Admin Aide VI/Clerk III MEBO
Step 3: Proceed to the Municipal Treasurer's Office for payment
The office will
- Receive payment and issue the official receipt
- Fee
- NBCDO schedule of fees and charges
- Time
- 10–15 minutes
- Handled by
- RCC III MTO, RCC II MTO
Step 4: Present the documents from the Bureau of Fire Protection
The office will
- Receive the documents from the Bureau of Fire Protection
- Fee
- Free
- Time
- 10–20 minutes
- Handled by
- Engineer I MEBO, Admin Aide VI/Clerk III MEBO
Claim
Step 5: Claim the Certificate of Occupancy
The office will
- Receive the official receipts and order of payment
- Process and prepare the Certificate of Occupancy
- Release the Certificate of Occupancy
- Fee
- Free
- Handled by
- MEBO
Where to go
Office of the Municipal Engineer & Building Official
Allah Valley Drive, Surallah, South Cotabato
Problems or feedback?
The Municipal Internal Audit Service Office (MIASO) handles complaints: miaso.surallah@gmail.com · (083) 238-3618. How it works
Source: LGU Surallah Citizen's Charter 2026 (1st edition), pages 94–105. Open the PDF at this page ↗ If anything here differs from the PDF, the PDF is the official version.