Building permit

In the charter: Issuance of Building Permit

Under PD 1096 (the National Building Code), the Office of the Municipal Engineer & Building Official (MEBO) issues building permits for the construction, alteration, repair, conversion, use, occupancy, moving, demolition of, and addition to public and private buildings and structures — except traditional indigenous family dwellings and projects under BP 220 (economic and socialized housing). A building permit is required before any building or structure is constructed, altered, repaired, converted, used, occupied, moved or demolished.

Processing time
Not stated in the charter
Fees
Fees apply. See the steps below.
Who can apply
Anyone
Type of transaction
Simple, complex or highly technical · government to citizen · government to business · government to government

Simple applications cover private garages up to 90 m², carports, sheds, agricultural buildings, fences over 1.80 m, tanks and towers; repairs that don't change approved plans; demolition of a single residential structure up to 300 m² and three storeys; signage; and stand-alone mechanical, sanitary, electrical, electronics and accelerograph permits (page 79).

Complex and highly technical applications follow the same steps with longer review times (pages 84–93). The charter does not print a total processing time for these applications.

Fees are computed from the National Building Code schedule of fees and other charges on pages 108–125 of the charter.

What to bring

Tick items off as you gather them. Nothing is saved or sent anywhere.

Conditional requirements

Step by step

  1. Apply

    Step 1: Submit the application forms and documentary requirements

    The office will

    • Receive and assess the submitted plans and documents
    • Conduct site inspection and verification
    • Evaluate the plans
    Fee
    Free
    Handled by
    Engineer I, Engineer II MEBO
  2. Pay

    Step 2: Receive the order of payment, have the plans endorsed, and pay the corresponding fees

    The office will

    • Calculate and prepare building fees based on the NBCDO schedule of fees and other charges
    • Issue the order of payment
    Fee
    Based on the NBCDO schedule of fees and other charges
    Handled by
    Engineer I, Engineer II MEBO
  3. Step 3: Proceed to the Municipal Treasurer's Office for payment

    The office will

    • Receive payment and issue the official receipt
    Fee
    NBCDO schedule of fees and charges
    Time
    10 minutes
    Handled by
    RCC III MTO, RCC II MTO
  4. Step 4: Present the documents from the Bureau of Fire Protection

    The office will

    • Receive the documents from the Bureau of Fire Protection
    Fee
    Free
    Time
    10–20 minutes
    Handled by
    Engineer I MEBO, Admin Aide VI/Clerk III MEBO
  5. Claim

    Step 5: Claim the approved Building Permit and ancillary permits

    The office will

    • Receive the order of payment and official receipts
    • Process and prepare the Building Permit
    • Release the approved permit, plans and other documents
    Fee
    Free
    Handled by
    MEBO

Where to go

Office of the Municipal Engineer & Building Official

Allah Valley Drive, Surallah, South Cotabato

Problems or feedback?

The Municipal Internal Audit Service Office (MIASO) handles complaints: miaso.surallah@gmail.com · (083) 238-3618. How it works

Source: LGU Surallah Citizen's Charter 2026 (1st edition), pages 79–93. Open the PDF at this page ↗ If anything here differs from the PDF, the PDF is the official version.